Apply to RWE Baustrom

instagram viewer

There are various reasons why you need to apply for site power, such as with RWE. It can be a new building or the conversion of an existing building that does not have a power connection.

You probably know them from many construction sites. We are talking about junction boxes that are in front of it. This is the necessary supply of site electricity, without which such a project would be impossible. But here, too, you have to pay attention to a few things before you get such a box. As with many other things, you have to apply for this first. How this works at RWE, for example, is to be explained to you below.

Apply to RWE Baustrom - the requirements

  • When you apply to RWE Baustrom, you as a customer have to do a lot yourself. This includes, for example, that you have to hire an electrician who will later ensure that a site power distributor is connected to the power supply.
  • So that the electricity supplier can get an idea of ​​the construction project, you must enclose an official site plan. You also need a floor plan that shows where the network connection room is located.

This is how you proceed when you apply for site electricity

  • In the case of a new building project, the application for an electricity connection and the at the same time necessary provision of the site electricity belong together. You can watch the application either get it directly from RWE or fill it out on the Internet and print it out.
  • When applying, please note that site electricity is only available for a maximum of 18 months. After you have entered your personal data, you still have to specify how the power supply is presented, i.e. how it should be used, whether private, commercial or mixed.
  • How do I register electricity? - That's how it works

    Are you moving into a new apartment or even your own home? Then imagine ...

  • RWE also needs information about the power requirements of the site electricity. The best way to do this is to speak to your electrician. After you have collected all the information and the necessary documents to apply for, submit the documents to the electricity supplier RWE.